Client: Meridian Fabrication Co. (fictional) — 22-employee custom metal fabricator, Hobart IN; 3 CNC cutting machines + office suite · Date: Oct 2026 · Scope: Office IT, CNC/machine PCs (OT), vendor remote support, accounting, customer CAD files · Auditor: Deep Vector Labs
| Asset | Data held | Impact if lost/public |
|---|---|---|
| CNC controllers ×3 (Win7 Embedded / XP panels) | Machine programs, uptime — the plant's revenue engine | EXISTENTIAL stopped machines = stopped revenue; corrupt program = scrap or injury |
| Customer CAD/CAM job library (NAS) | Proprietary & NDA-wrapped parts drawings, incl. defense-adjacent subcontracts | CRITICAL contract loss + NDA breach litigation |
| Accounting workstation + QuickBooks (NAS) | Bank details, payroll, customer/vendor records | HIGH payment fraud pivot; 9-year-old degraded NAS is a hardware clock |
| Vendor remote-support appliance (machine OEM) | Permanent inbound bridge to the plant flat network | HIGH supply-chain entry point (documented pattern in industrial incidents) |
| Office email (5 seats, Okta-less O365) | Quotes, POs, customer contacts | MEDIUM BEC pivot; MFA on ✓ (one thing that's right) |
| # | Finding | Detail | Severity |
|---|---|---|---|
| F1 | IT/OT flat network — one switch, one domain | Office malware can see CNC controllers directly. From the reception PC we enumerated all three controllers in under two minutes (consented test, off-shift). | CRITICAL |
| F2 | CNC controllers run EOL Windows (7 Embedded / XP) | No patches since 2015–2019; no EDR supportable. OEM says replacement means machine downtime + recertification ≈ $40K/machine. | CRITICAL |
| F3 | NAS RAID-5 degraded for weeks (one failed disk, alarm active) | Second disk failure now = total library loss. Also hosts the QuickBooks company file. This is a today-problem. | CRITICAL |
| F4 | Vendor remote bridge permanently open, unmanaged credentials | OEM tech account password rotated never; appliance firmware 4 years stale; no logging of vendor sessions reaching IT or management. | HIGH |
| F5 | CAD library permissions "Everyone: Full Control" | Any office login — including past interns' accounts still enabled — can read/exfiltrate every drawing. | HIGH |
| F6 | 14 stale AD/local accounts incl. 4 former employees | Two still had VPN-capable group membership from a legacy experiment. | HIGH |
| F7 | Backups: robocopy to the same NAS | "Backup" of the library lives in the same blast radius as the library. No offline or off-site tier. | HIGH |
| F8 | No network monitoring or syslog anywhere | Nothing would record an intruder touching a controller. Safety PLC interlocks are hardware (good), but data integrity on job files is unverified. | MEDIUM |
The classic: office phish → flat network (F1) → controllers encrypted (F2 can't be remediated/patched, only isolated) → production dark for a week+. Estimated loss ≈ $310K (quoted contracts + overtime catch-up).
Stale account (F6) or insider (F5) walks out with NDA drawings. Defense-adjacent customers audit; the contract evaporates. This sector treats IP loss as terminal.
OEM's support account reused elsewhere (F4) → attacker rides the legitimate appliance inbound → straight onto controllers. Observed repeatedly in published industrial incident reports.
Not an attacker at all: F3's degraded RAID fails a second disk mid-run — the most likely "event" on this list, and already in progress.
Overall 8.1/10 — the highest-severity sample in this set, driven by an unsegmented IT/OT boundary against end-of-life controllers plus an already-active hardware failure. OT risk lens aligns to IEC 62443 zones/conduits language; safety functions themselves were hardware-interlocked and out of cyber scope — stated candidly to keep the rating honest.
Hot-spare installed and rebuild verified; nightly encrypted library backup to cloud with 180-day retention + a weekly restore checksum. The "already in progress" incident gets closed first.
Dedicated industrial firewall/VLAN: controllers + engineering PCs in a zone that office machines cannot route to; only the engineering file-gateway bridges, and that two-way conduit is firewall-logged.
Appliance moved to always-blocked-unless-enabled; a "vendor access requested/authorized/logged" ticket ritual per session; stale firmware updated by the OEM as a contract deliverable.
Stale accounts disabled (scripted report monthly); CAD library restricted to engineering group; DLP-light folder auditing on the drawings share.
Since patching/replacement is off the table near-term: application allowlisting where supported, USB port control discipline, host firewall rules denying SMB from non-engineering hosts, and one-way job-file flow patterns documented per IEC 62443 zone guidance.
Syslog from firewall + servers to a lightweight collector; a laminated "machines down — who to call" card next to the shop phone; annual tabletop drill with the foreman.